October 25, 2024
Construction Advisory
Please be advised that this schedule may change due to weather and existing conditions found while performing the tasks below. This work may impact traffic and require lane and sidewalk closures limiting access to driveways and entrances to businesses.
What to Expect for the Week of October 28th to November 1st, 2024
Walkway at 35 Main Street
Walkway at 77 Main
Work at 36 Main
Miscellaneous work along the corridor
Detours or Alternating Traffic will be used as necessary.
All 12 transformers have been delivered and installed.
Awaiting schedule from Eversource to begin overhead to underground services.
Awaiting schedule from Verizon to complete overhead utility transfers on west side of the project.