Use the pulldown menu below to view prior construction updates.
September 27, 2024
Construction Advisory
Please be advised that this schedule may change due to weather and existing conditions found while performing the tasks below. This work may impact traffic and require lane and sidewalk closures limiting access to driveways and entrances to businesses.
What to Expect for the Week of September 30th to October 4th, 2024
Overhead utility line transfer work continues on the west side of the project.
Brick strip installation will continue along the east side of the project.
Electrical connections into buildings may begin.
Detours or Alternating Traffic will be used as necessary.
All 12 transformers have been delivered and installed.
Eversource crews are working on the preliminary work associated with the transformers.
The start of overhead to underground should begin in early October.