Use the pulldown menu below to view prior construction updates.
July 18, 2025
Project Update/Anticipated Work
Comcast is continuing to cut over services. Due to a delay in one of their services, the final completion date was pushed out; still on track to be done this month.
AT&T - On track to complete work mid-July.
Comm-tract (town fiber network) - Substantially complete; will return to transfer one final line on 7/24.
Verizon expected onsite the week of July 21st; work will include transferring current equipment on poles, placing new fiber and removing some of the old poles. No date yet provided for the completion of their work.
Amorello will be onsite on 7/24 to assist Dagle Electric with utility work at the corner of Meserve and Main Street.
Amorello will fully mobilize once the utility work is complete. They may schedule work on the west side of the project pending the removal of old utility poles and the progress of utility companies’ work. Some remaining work on the east side of the project may be scheduled July or August, pending utility work Progress.
Additional Landscaping Changes - MassDOT is currently reviewing. When their review is completed, they will send comments to Amorello and the Town.
Weekly Construction Advisories will resume when there are weekly updates on the project. Until then the Town will send Project Updates as needed.