Use the pulldown menu below to view prior construction updates.
August 12, 2026
Project Update
Please be advised that this schedule may change due to weather and existing conditions found while performing the tasks below. This work may impact traffic and require lane and sidewalk closures.
Project Status/Anticipated Work
Paving on the east side of the project from the Fire Station to Ray Street is scheduled for the week of August 17th. Paving preparation is in progress.
Driveway work is scheduled for the Fire Station and 77 Main Street on Friday, 8/14 and Monday, 8/17. One side of the driveway will remain open at all times.
Driveway work is scheduled for the west driveway at Town Hall and BoMain Pizza on Monday, 8/17. The east driveway will be available for 2 way traffic.
Milling for transitions (side roads) will be done on Monday, 8/17.
Road paving is scheduled for Tuesday, 8/19 and Wednesday, 8/20 from the Fire Station to the east end of the project, including side streets within the project area, and Grove Street and Cedar Street within the project area.
This schedule is subject to change due to weather and contractor availability.
The Pleasant Street detour will continue to be used through 8/21.
Detour Schedule
Hours: 7:00 AM - 3:00 PM
Monday-Friday, August 10-14
Monday-Friday, August 17-21
Eastbound Detour Route
Pleasant Street → Maple Street → Hayden Rowe Street
Additional detours and lane closures will be used as needed.
Please plan ahead, allow extra travel time, and follow posted detour signs. We appreciate your patience and cooperation as work continues to improve Main Street.